← Behind the marquee
One job at a time
The construction schedule
There’s a lot to do before the next night at the Fox. Here’s the contractor’s plan, from the first paperwork to the last repairs.
McKinstry schedule · Updated
The schedule covers 102 tasks by work area. Each progress figure is the contractor’s October 27 record for that task.
Before construction
-
Sign contract
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Bonds and insurance
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Safety paperwork
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Submittals
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Site survey
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Exterior photographs before construction
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Interior photographs before construction
- Planned start
- Planned finish
- Recorded progress
- 100%
Ceiling abatement
-
County abatement award delay
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Install scaffolding at balcony beam
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Install scaffolding at centre of theatre
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Ceiling plaster abatement
- Planned start
- Planned finish
- Recorded progress
- 100%
Above the balcony
-
Install temporary supports at balcony beam
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Cut back ceiling joists
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Add engineered timber alongside beams
- Planned start
- Planned finish
- Recorded progress
- 99%
-
Hang joists from new timber beams
- Planned start
- Planned finish
- Recorded progress
- 99%
-
Structural inspection
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Remove balcony supports
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Scaffolding available for building systems work
- Planned start
- Planned finish
- Recorded progress
- 0%
Above the centre of the theatre
-
Install beams at roof level
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install blocking between beams
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Raise sagging ceiling framing to level
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install straps and timber braces
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Structural inspection
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Scaffolding available for building systems work
- Planned start
- Planned finish
- Recorded progress
- 0%
Ceiling plaster
-
Plaster the theatre ceiling
- Planned start
- Planned finish
- Recorded progress
- 0%
Ceiling paint
-
Paint the theatre ceiling
- Planned start
- Planned finish
- Recorded progress
- 0%
Door to the adjacent building
-
Cut in lintel above doorway
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Cut doorway
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Demolish doorway
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install hollow metal door frame
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install door
- Planned start
- Planned finish
- Recorded progress
- 0%
Above the stage
-
Install scaffolding at stage
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Structural framing at roof
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Lower scaffolding to rigging platform
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Structural framing at rigging platform
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Structural inspection
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Scaffolding available for building systems work
- Planned start
- Planned finish
- Recorded progress
- 0%
Balcony scaffolding
-
Remove balcony scaffolding
- Planned start
- Planned finish
- Recorded progress
- 0%
Centre scaffolding
-
Remove centre theatre scaffolding
- Planned start
- Planned finish
- Recorded progress
- 0%
Stage scaffolding
-
Remove stage scaffolding
- Planned start
- Planned finish
- Recorded progress
- 0%
Down in the basement
The basement work includes drainage and measures to protect the theatre from water.
-
Lead paint abatement
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Mold abatement
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Mold clearance sample
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove basement woodwork
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Cut concrete floor for French drain
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Remove concrete floor
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Excavate for French drain
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Excavate sump pit
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install French drain
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install gravel at French drain
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install sump pit and pump
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Pour concrete patch
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Repair damaged basement masonry
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Reinstall wall framing
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Paint basement
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Reinstall basement woodwork
- Planned start
- Planned finish
- Recorded progress
- 0%
Roof hatch and ladder
-
Frame new roof hatch
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install roof hatch
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Roofing at hatch
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Install new ladder
- Planned start
- Planned finish
- Recorded progress
- 0%
Outside, below street level
-
Set up stormwater management
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove fire escape stair
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove gas meter and excess piping
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove exterior stair and retaining wall
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Excavate 18 inches below grade for waterproofing
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Waterproof back wall 18 inches below grade
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Install temporary supports
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove basement door and frame
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Block in door opening
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Waterproof exterior wall
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Insulate wall
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Remove temporary supports
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Backfill and compact
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Drainage plan and evacuation delay
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Prepare and compact ground for sidewalk and drainage channel
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Cut and remove front sidewalk
- Planned start
- Planned finish
- Recorded progress
- 100%
-
Drill fire escape foundations
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Form and pour retaining wall at coal chute
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Pour foundations and retaining wall
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Form and pour landing at base of stair
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Form sidewalk
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Form drainage channel
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Pour and finish concrete
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Strip concrete forms
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Backfill and final grading
- Planned start
- Planned finish
- Recorded progress
- 0%
Brick, windows and marquee
The plan lists repairs to the brickwork, windows, and marquee.
-
Evaluate boarded windows for replacement
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Repoint and repair brick
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Rebuild existing windows
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Repair roof at marquee sign
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Repair sign
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Repair stucco
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Paint exterior
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Build scaffolding inside marquee sign
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Clean primary steel frame with wire wheel
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Paint steel frame with zinc paint
- Planned start
- Planned finish
- Recorded progress
- 0%
Finishing and acceptance
-
Substantial completion
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Punch list
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Final acceptance
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Deliver closeout records
- Planned start
- Planned finish
- Recorded progress
- 0%
Structural change order
-
Approve structural change order
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Abatement for structural change
- Planned start
- Planned finish
- Recorded progress
- 0%
-
Construction for structural change
- Planned start
- Planned finish
- Recorded progress
- 0%