The construction schedule

There’s a lot to do before the next night at the Fox. Here’s the contractor’s plan, from the first paperwork to the last repairs.

McKinstry schedule · Updated

The schedule covers 102 tasks by work area. Each progress figure is the contractor’s October 27 record for that task.

Before construction

  • Sign contract

    Planned start
    Planned finish
    Recorded progress
    100%
  • Bonds and insurance

    Planned start
    Planned finish
    Recorded progress
    100%
  • Safety paperwork

    Planned start
    Planned finish
    Recorded progress
    100%
  • Submittals

    Planned start
    Planned finish
    Recorded progress
    100%
  • Site survey

    Planned start
    Planned finish
    Recorded progress
    100%
  • Exterior photographs before construction

    Planned start
    Planned finish
    Recorded progress
    100%
  • Interior photographs before construction

    Planned start
    Planned finish
    Recorded progress
    100%

Ceiling abatement

  • County abatement award delay

    Planned start
    Planned finish
    Recorded progress
    100%
  • Install scaffolding at balcony beam

    Planned start
    Planned finish
    Recorded progress
    100%
  • Install scaffolding at centre of theatre

    Planned start
    Planned finish
    Recorded progress
    100%
  • Ceiling plaster abatement

    Planned start
    Planned finish
    Recorded progress
    100%

Above the balcony

  • Install temporary supports at balcony beam

    Planned start
    Planned finish
    Recorded progress
    100%
  • Cut back ceiling joists

    Planned start
    Planned finish
    Recorded progress
    100%
  • Add engineered timber alongside beams

    Planned start
    Planned finish
    Recorded progress
    99%
  • Hang joists from new timber beams

    Planned start
    Planned finish
    Recorded progress
    99%
  • Structural inspection

    Planned start
    Planned finish
    Recorded progress
    0%
  • Remove balcony supports

    Planned start
    Planned finish
    Recorded progress
    0%
  • Scaffolding available for building systems work

    Planned start
    Planned finish
    Recorded progress
    0%

Above the centre of the theatre

  • Install beams at roof level

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install blocking between beams

    Planned start
    Planned finish
    Recorded progress
    0%
  • Raise sagging ceiling framing to level

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install straps and timber braces

    Planned start
    Planned finish
    Recorded progress
    0%
  • Structural inspection

    Planned start
    Planned finish
    Recorded progress
    0%
  • Scaffolding available for building systems work

    Planned start
    Planned finish
    Recorded progress
    0%

Ceiling plaster

  • Plaster the theatre ceiling

    Planned start
    Planned finish
    Recorded progress
    0%

Ceiling paint

  • Paint the theatre ceiling

    Planned start
    Planned finish
    Recorded progress
    0%

Door to the adjacent building

  • Cut in lintel above doorway

    Planned start
    Planned finish
    Recorded progress
    0%
  • Cut doorway

    Planned start
    Planned finish
    Recorded progress
    0%
  • Demolish doorway

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install hollow metal door frame

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install door

    Planned start
    Planned finish
    Recorded progress
    0%

Above the stage

  • Install scaffolding at stage

    Planned start
    Planned finish
    Recorded progress
    100%
  • Structural framing at roof

    Planned start
    Planned finish
    Recorded progress
    0%
  • Lower scaffolding to rigging platform

    Planned start
    Planned finish
    Recorded progress
    100%
  • Structural framing at rigging platform

    Planned start
    Planned finish
    Recorded progress
    100%
  • Structural inspection

    Planned start
    Planned finish
    Recorded progress
    0%
  • Scaffolding available for building systems work

    Planned start
    Planned finish
    Recorded progress
    0%

Balcony scaffolding

  • Remove balcony scaffolding

    Planned start
    Planned finish
    Recorded progress
    0%

Centre scaffolding

  • Remove centre theatre scaffolding

    Planned start
    Planned finish
    Recorded progress
    0%

Stage scaffolding

  • Remove stage scaffolding

    Planned start
    Planned finish
    Recorded progress
    0%

Down in the basement

The basement work includes drainage and measures to protect the theatre from water.

  • Lead paint abatement

    Planned start
    Planned finish
    Recorded progress
    100%
  • Mold abatement

    Planned start
    Planned finish
    Recorded progress
    100%
  • Mold clearance sample

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove basement woodwork

    Planned start
    Planned finish
    Recorded progress
    0%
  • Cut concrete floor for French drain

    Planned start
    Planned finish
    Recorded progress
    0%
  • Remove concrete floor

    Planned start
    Planned finish
    Recorded progress
    0%
  • Excavate for French drain

    Planned start
    Planned finish
    Recorded progress
    0%
  • Excavate sump pit

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install French drain

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install gravel at French drain

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install sump pit and pump

    Planned start
    Planned finish
    Recorded progress
    0%
  • Pour concrete patch

    Planned start
    Planned finish
    Recorded progress
    0%
  • Repair damaged basement masonry

    Planned start
    Planned finish
    Recorded progress
    0%
  • Reinstall wall framing

    Planned start
    Planned finish
    Recorded progress
    0%
  • Paint basement

    Planned start
    Planned finish
    Recorded progress
    0%
  • Reinstall basement woodwork

    Planned start
    Planned finish
    Recorded progress
    0%

Roof hatch and ladder

  • Frame new roof hatch

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install roof hatch

    Planned start
    Planned finish
    Recorded progress
    0%
  • Roofing at hatch

    Planned start
    Planned finish
    Recorded progress
    0%
  • Install new ladder

    Planned start
    Planned finish
    Recorded progress
    0%

Outside, below street level

  • Set up stormwater management

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove fire escape stair

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove gas meter and excess piping

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove exterior stair and retaining wall

    Planned start
    Planned finish
    Recorded progress
    100%
  • Excavate 18 inches below grade for waterproofing

    Planned start
    Planned finish
    Recorded progress
    100%
  • Waterproof back wall 18 inches below grade

    Planned start
    Planned finish
    Recorded progress
    100%
  • Install temporary supports

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove basement door and frame

    Planned start
    Planned finish
    Recorded progress
    100%
  • Block in door opening

    Planned start
    Planned finish
    Recorded progress
    100%
  • Waterproof exterior wall

    Planned start
    Planned finish
    Recorded progress
    100%
  • Insulate wall

    Planned start
    Planned finish
    Recorded progress
    100%
  • Remove temporary supports

    Planned start
    Planned finish
    Recorded progress
    100%
  • Backfill and compact

    Planned start
    Planned finish
    Recorded progress
    100%
  • Drainage plan and evacuation delay

    Planned start
    Planned finish
    Recorded progress
    100%
  • Prepare and compact ground for sidewalk and drainage channel

    Planned start
    Planned finish
    Recorded progress
    100%
  • Cut and remove front sidewalk

    Planned start
    Planned finish
    Recorded progress
    100%
  • Drill fire escape foundations

    Planned start
    Planned finish
    Recorded progress
    0%
  • Form and pour retaining wall at coal chute

    Planned start
    Planned finish
    Recorded progress
    0%
  • Pour foundations and retaining wall

    Planned start
    Planned finish
    Recorded progress
    0%
  • Form and pour landing at base of stair

    Planned start
    Planned finish
    Recorded progress
    0%
  • Form sidewalk

    Planned start
    Planned finish
    Recorded progress
    0%
  • Form drainage channel

    Planned start
    Planned finish
    Recorded progress
    0%
  • Pour and finish concrete

    Planned start
    Planned finish
    Recorded progress
    0%
  • Strip concrete forms

    Planned start
    Planned finish
    Recorded progress
    0%
  • Backfill and final grading

    Planned start
    Planned finish
    Recorded progress
    0%

Brick, windows and marquee

The plan lists repairs to the brickwork, windows, and marquee.

  • Evaluate boarded windows for replacement

    Planned start
    Planned finish
    Recorded progress
    0%
  • Repoint and repair brick

    Planned start
    Planned finish
    Recorded progress
    0%
  • Rebuild existing windows

    Planned start
    Planned finish
    Recorded progress
    0%
  • Repair roof at marquee sign

    Planned start
    Planned finish
    Recorded progress
    0%
  • Repair sign

    Planned start
    Planned finish
    Recorded progress
    0%
  • Repair stucco

    Planned start
    Planned finish
    Recorded progress
    0%
  • Paint exterior

    Planned start
    Planned finish
    Recorded progress
    0%
  • Build scaffolding inside marquee sign

    Planned start
    Planned finish
    Recorded progress
    0%
  • Clean primary steel frame with wire wheel

    Planned start
    Planned finish
    Recorded progress
    0%
  • Paint steel frame with zinc paint

    Planned start
    Planned finish
    Recorded progress
    0%

Finishing and acceptance

  • Substantial completion

    Planned start
    Planned finish
    Recorded progress
    0%
  • Punch list

    Planned start
    Planned finish
    Recorded progress
    0%
  • Final acceptance

    Planned start
    Planned finish
    Recorded progress
    0%
  • Deliver closeout records

    Planned start
    Planned finish
    Recorded progress
    0%

Structural change order

  • Approve structural change order

    Planned start
    Planned finish
    Recorded progress
    0%
  • Abatement for structural change

    Planned start
    Planned finish
    Recorded progress
    0%
  • Construction for structural change

    Planned start
    Planned finish
    Recorded progress
    0%