Revitalization overview

Phase 2 · In progress

Behind the marquee, the work goes on.

Up on the roof. Down at the foundations. Above the balcony and stage. Take a look at the next stage of work inside the historic theatre at 715 Main.

A multi-decade plan

The next steps for the Fox

Phase 2 is part of the Fox’s multi-decade revitalization plan. Phase 1 repaired the roof and strengthened its structure. This next stage reaches into the rest of the theatre: the beams above us, the ground below us, the brickwork, and the building systems.

Some of the most important work will disappear above the ceiling or below the ground. For now, we can show you how new timber meets old brick, and why those repairs matter to the next night we spend together at the Fox.

From the construction files

A look at the work so far

These photos and field reports follow the work from August 2025 through October 2026. Each date marks a moment in the project. There is still work ahead.

  1. August 2025

    Up on the roof

    The construction photos take us onto the roof during work on the heating and cooling system.

  2. November 2025

    Down to the foundations

    Excavation and formwork along the outside walls show how much of this work happens below street level.

  3. September–October 2026

    Above the balcony and stage

    New timber, temporary supports and scaffolding fill the construction photos. The October 1 engineering visit identified connections and other work still to finish.

  4. October 20, 2026

    The latest look inside

    The latest photos in this gallery show new timber reinforcement alongside the building’s old brick and joists.

The construction checklist

There’s still
work to do.

Open items from the construction files, reviewed . Completion has not been confirmed for these items.

  • To finish

    Finish the structural details

    The October 1 engineering visit identified beam connections and other details still to finish above the balcony and stage.

  • To finish

    Keep water out of the basement

    Water was still getting in at the September 30 visit. The plans call for drains, a sump pump and repairs below the room.

  • To confirm

    Connect the building systems

    Electrical work serves the heating and cooling, stage lights and sump pump. Installation and testing still need confirmation.

  • Pricing and scope to confirm

    Repair the brick, windows and marquee

    These repairs appear in the design. The architect has requested masonry prices; the work that can go ahead depends on funding.

  • To finish

    Finish the roof access

    The October 16 schedule carries the roof hatch and new ladder into January 2027. The team needs to confirm the dates.

  • Acceptance ahead

    Complete the final checks

    Finish the remaining work, resolve the punch list and confirm acceptance. The schedule’s November milestones and January tasks still need to agree.

The September 30 visit found water still coming into the basement. On October 21, our architect asked for prices for priority brickwork repairs and the full masonry work. How much can go ahead depends on the funding available.

The schedule updated October 16 carries basement work through January 11, 2027, and roof-hatch work through January 14. It also keeps earlier November completion and acceptance dates. The project team needs to settle those dates. There is no opening date to announce yet.

A drawing shows the plan. A photo shows a moment in the job. We will keep sharing both, and tell you when the work is finished and accepted.

See the construction schedule

With a lot of help

A big hand for the people making this possible.

State and local partners, foundations and community donors have backed the Fox along the way. We are grateful for every part they play.

And to everyone who has given to the Fox: thank you. You are part of this story, too.

This project was funded in part with a grant from History Colorado, the State Historical Fund.

A little closer

Three stories from behind the marquee

Take a look below the sidewalk, up above the balcony, and at the partners supporting the Fox’s long-term revitalization.

Many hands, one Fox

The organizations moving the work forward

The next chapter

The next phase of revitalization

The beams, drains and plaster have a job to do before the lights go down. The next chapter includes seats, sound, access devices, the lobby and concessions. There are specific projects you can help move forward. We will share an opening date for the main auditorium when the work and required approvals are complete.